Private contractors, utility companies, and property owners proposing work within the public right-of-way must obtain an Encroachment Permit before beginning any work.
Utility companies performing emergency work should refer to Policy E-2024-001 Utility Company Emergency Work.
Applications for the following permit types can be submitted electronically through the City's etrakit portal:
- Minor Encroachment Permits
- Major Encroachment Permits
- Utility Encroachment Permits
Minor Encroachment Permits are issued for work within the public right-of-way that is not associated with a project requiring Planning entitlement approval. Major Encroachment Permits are issued for work within the public right-of-way associated with a project that has completed the Planning entitlement process and received all required Planning approvals.
Applicants can submit applications, upload supporting documents, monitor application status, and communicate with City staff through the etrakit portal.
If you need assistance with the etrakit portal, application requirements, or the permitting process, please contact Public Works Development Engineering at (707) 449-5170 or email PublicWorks@cityofvacaville.gov.
Review times vary depending on the complexity of the proposed work. Applicants should generally allow approximately four weeks for permit review. If public improvement plans are required, typical review times are six weeks for the initial submittal and three weeks for subsequent resubmittals.
Visit the etrakit Portal.
Scheduling Required Inspections
After your encroachment permit has been issued, and before any work can begin, you must schedule a Preconstruction Conference with Public Works Construction staff. To schedule a conference, please email Public Works Inspection at PublicWorks_InspectionRequest@CityOfVacaville.gov.
Following the Preconstruction Conference, work may begin in accordance with the approved permit.
A Construction Inspector must be notified each day work will occur. Inspection requests must be submitted by email to Public Works Inspection at PublicWorks_InspectionRequest@CityOfVacaville.gov before 7:00a.m and should include the following:
- Project Name
- Project Location
- Encroachment Permit Number
- Contact Name
- Contact Phone Number
- Type of Inspection Requested
- Requested Inspection Time
A Construction Inspector will be assigned and will make every effort to perform the inspection as close as possible to the requested time.